APAC BESS daily brief · 11 Nov 2026
the Philippines · Project BriefPetroEnergy's EcoSolar energizes 22.5 MW/45 MWh Panitan grid-forming battery in Capiz, begins testing
EcoSolar Energy Corporation, a unit of PetroEnergy Resources Corporation, has energized the 22.5 MW/45 MWh Panitan Energy Storage Project in Capiz, Philippines, and started generation testing. Testing followed approval of its market registration and a provisional connection certificate from the grid operator.
Project
- Located in Capiz in the Visayas; uses grid-forming technology.
- Market registration approved and provisional connection certificate received from the grid operator.
Financing
- Lenders, tariff and contract structure: not publicly disclosed.
Sources: SolarQuarter
Japan · Project Finance BriefA.D.Works borrows ¥1,143.1m from Chiba Bank for two high-voltage grid batteries in Taki, Mie and Kumamoto City
A.D.Works, part of the ADWorks Group, signed loan contracts with Chiba Bank under its 'Chibagin Leaders Loan NEXT (environmental equipment)' product, totalling ¥1,143.1m across two loans. The money funds the acquisition of two high-voltage grid-connected battery sites in Taki, Mie Prefecture, and Kumamoto City.
Project
- The two sites are in Taki, Taki District, Mie Prefecture, and Kumamoto City, Kumamoto Prefecture; both are high-voltage grid-connected batteries.
- MW/MWh of each project: not publicly disclosed.
Financing
- Lender: Chiba Bank, under its 'Chibagin Leaders Loan NEXT (environmental equipment)' product.
- Amount: ¥1,143.1m across two loans; contracts signed in September 2026.
- Interest rate, tenor and security structure: not publicly disclosed.
- View: a regional bank lending through an environmental-equipment product shows battery finance in Japan widening beyond large project finance to regional-bank corporate and equipment loans for small high-voltage sites.
Sources: PR TIMES (A.D.Works)
Japan · Project BriefNihon Chikudenchi and Remixpoint fund start 1,996 kW/8,146 kWh battery in Kainan, Wakayama
Nihon Chikudenchi said the NC Kainan Kizu battery in Kainan, Wakayama Prefecture, developed through a fund formed jointly with Remixpoint, began receiving power on 9 November 2026. The 1,996 kW/8,146 kWh site will serve the balancing market, JEPX wholesale market and capacity market.
Project
- Size: 1,996 kW/8,146 kWh; operation start: 9 November 2026.
- Equipment: TMEIC system with CATL batteries; design and construction by Y-Just.
- Revenue streams: balancing market, JEPX and capacity market.
Financing
- Developed through a fund formed jointly by Nihon Chikudenchi and Remixpoint; fund size and lenders not publicly disclosed.
Sources: PR TIMES (日本蓄電池)
Global · Policy BriefNetherlands sets 110 GWh battery storage target for 2040 to ease grid congestion
The Dutch government set a benchmark of 110 GWh of battery storage by 2040 in a new Energy Storage Policy Agenda, more than a 50-fold increase on end-2025 capacity. The agenda contains 25 actions, with progress tracked annually by RVO.
Financing
- View: a clear long-term volume target plus grid-access and tariff reform should improve lenders' visibility on Dutch storage revenues.
Policy
- Co-authored with Netbeheer Nederland, Energy Storage NL, municipal and provincial governments and the regulator ACM.
- Flexible grid connection contracts and new tariff/compensation structures are intended, without further specifics.
Sources: ESS News
Global · Policy BriefIndia: NHPC tenders 800 MW of BESS at 1.2 GW Jalaun Solar Park in two configurations (4,800 MWh / 3,200 MWh)
NHPC, on behalf of Bundelkhand Saur Urja Ltd (BSUL), has invited bids for BESS at the 1.2 GW Jalaun Solar Park in Uttar Pradesh, selected by tariff-based bidding on a composite solar-plus-storage tariff. Configuration I pairs 300 MW of solar with 800 MW/4,800 MWh of BESS; Configuration II pairs 600 MW of solar with 800 MW/3,200 MWh.
Project
- Storage is co-located with and charged from the park's solar; the park's solar developers are Coal India and NLC India Renewables.
Financing
- The winner signs a PPA with BSUL; performance bank guarantees are due after the letter of award and before the PPA.
- Bid deadline and guarantee amounts: not publicly disclosed in the reports.
Policy
- BSUL is a joint venture of NHPC and UPNEDA; build-own-operate model, with a reverse auction on the CPPP portal.
- A bidder may win up to 50% of total contracted capacity and at most two location blocks; the tender notice was signed on 4 November 2026.
Sources: ESS News / pv magazine India · SolarQuarter
China · Project BriefHuaneng connects 5.5 MW/1.375 MWh dual-flywheel frequency regulation system at Lanzhou plant
China Huaneng Group connected a dual-flywheel frequency regulation system, rated 5.5 MW/1.375 MWh in total, at its Lanzhou combined heat and power plant on 6 November. Huaneng claims the 5 MW/1.25 MWh primary unit is China's highest-power single flywheel; its performance figures have not been independently verified.
Project
- Primary unit: 5 MW/1.25 MWh, up to 3,200 rpm; secondary unit: 0.5 MW/125 kWh inertia flywheel.
- Huaneng cites response time below 100 milliseconds and regulation accuracy above 99.5% (company figures, not independently verified).
- Installation and a 168-hour continuous trial run were completed in December 2025; development was led by Huaneng's Xi'an Thermal Power Research Institute.
Financing
- Huaneng's stated rationale includes cutting ancillary-service penalty costs and earning ancillary-service revenue; investment amount not publicly disclosed.
Sources: ESS News