APAC BESS daily brief · 26 Nov 2026
South Korea · Project Finance BriefBS Hanyang's Gwangyang ESS (96 MW / 576 MWh) construction contract extended to July 2027, clouding the year-end build target
The construction contract end date for the Gwangyang ESS that BS Hanyang and Korea Southern Power won in the central contract market moved from 31 March to 31 July 2027; the article gives no reason. Winning bidders were reportedly required to finish installation by end-December 2026, and the project SPC has raised KRW 40.9bn in a rights offering.
Project
- Gwangyang: 96 MW / 576 MWh; with the Goheung (Naro) site, 192 MW / 1,152 MWh in total
- Construction contract end date: 31 March 2027 → 31 July 2027
- Korea Southern Power's public data shows construction from May to December 2026
Financing
- SPC (Gwangyang Hwanggeum Energy Storage) rights offering of KRW 40.9bn: BS Hanyang KRW 11.8bn; Korea Southern Power and Korea Giga Platform KRW 29.1bn
- BS Hanyang's stake fell from 100% to 50%
- Debt terms: Not publicly disclosed
- View: if the delay shifts COD, it could affect contract milestones under the central contract market and loan drawdown schedules.
Policy
- Awarded in the first nationwide ESS central contract market round in 2025 (15-year contracts), which awarded 563 MW in total
- Bidders were reportedly required to complete installation by end-December 2026; whether the contract end date equals completion, and the COD, remain to be confirmed
Sources: Polinews
Global · Market BriefIndia: POWERGRID extends bid deadline to 25 November for five 100 MW/400 MWh BESS packages (2,000 MWh total) in Andhra Pradesh
In a 20 November notice, POWERGRID moved the soft-copy bid deadline for five BESS packages at the Rayalaseema Thermal Power Plant (AP-BESS-01 to 05, each 100 MW/400 MWh, 500 MW/2,000 MWh in total) from 20 to 25 November. The packages use tariff-based competitive bidding on a build-own-operate model and are part of a 1,250 MW/5,000 MWh four-hour BESS plan in Andhra Pradesh.
Project
- Rayalaseema Thermal Power Plant: 5 × 100 MW/400 MWh
- Other sites in the plan: Talaricheruvu 250 MW/1,000 MWh and NP Kunta 500 MW/2,000 MWh (separate APCPDCL tender)
Financing
- Tariff ceiling and contract tenor: Not publicly disclosed
Policy
- Soft-copy bid deadline: 20 → 25 November; deadline to request bid documents: 18 → 23 November
- Model: TBCB on a BOO basis, domestic competitive bidding, single-stage two-envelope e-procurement
Sources: Saur Energy
Australia · Project BriefACEN Australia lodges EPBC referral for Queensland's Belyando Energy Project, including a ~500 MW / up to 1,600 MWh battery
The Australian subsidiary of Philippines-based ACEN this week lodged documents with the federal government under the EPBC Act for the Belyando Energy Project near the coal-mining town of Moranbah, Queensland, opening it to public comment. The park combines up to 440 MW of wind, 500 MW of solar and a battery of around 500 MW with up to 1,600 MWh.
Project
- Site: near the coal-mining town of Moranbah, central Queensland
- Wind: up to 440 MW (up to 55 turbines of around 8 MW each)
- Solar: 500 MW
- Battery: around 500 MW, up to 1,600 MWh
- The southern section was removed after koala and greater glider habitat was found
- Construction and operation dates: Not publicly disclosed
Financing
- Capex, financing and offtake: Not publicly disclosed
Policy
- Referral lodged under the federal EPBC Act for environmental approval, opening the project to public comment
Sources: RenewEconomy
Australia · Project BriefSquadron Energy proposes the 1,000 MW Cullen Bullen battery near Lithgow, NSW, with up to 8 hours of storage and a A$1.5bn cost
Andrew Forrest's Squadron Energy has filed a scoping report with NSW planning authorities for the Cullen Bullen battery about 25 km north of Lithgow: 1,000 MW with up to 8 hours of storage (up to 8,000 MWh per RenewEconomy's headline). The A$1.5bn project would connect to an existing 500 kV line, with construction targeted to start in 2030.
Project
- Site: about 25 km north of Lithgow and 130 km north-west of Sydney, on around 660 ha of already cleared grazing land
- Size: 1,000 MW with up to 8 hours of storage; LFP, likely with grid-forming inverters
- Connection: existing 500 kV transmission line (Transgrid's network, per ESD News)
- Timing: construction targeted to start in 2030; the project is at an early stage
Financing
- Project cost: A$1.5bn
- Financing, revenue contracts and offtaker: Not publicly disclosed
- View: at 8 hours, bankability would likely hinge on long-duration contracts (LDS/CIS-type arrangements) to support debt sizing.
Policy
- Scoping report filed with the NSW planning authority (ESD News: plans submitted to the NSW Department of Planning and Environment)
- A voluntary planning agreement with Lithgow City Council is planned, with benefit sharing of A$150 per MWh per year
Sources: RenewEconomy · ESD News